2026-09-09 · Economia
Genera responde ao Negociado sobre frota TM2500 (San Juan/Palo Seco)
On September 9, 2026, Genera PR LLC filed at the Energy Bureau (NEPR-MI-2024-0005) a compliance motion to the August 31 Resolution and Order on the status, availability, operation and maintenance of the temporary generation fleet (TM2500) at San Juan and Palo Seco under the Priority Stabilization Plan. This note anchors that filing; ROI ≠ September 9 blackout.
The case record recalls PREPA acquired fourteen TM2500 units (ten in San Juan, four in Palo Seco) and that the PSP plans to run them through December 31, 2027 given their weight in system stability. Genera’s answers discuss hot-sections, forced outages, GE/other vendor contracts and return times — detail the Bureau sought to oversee backup generation.
Temporary-turbine availability ≠ 24/7 service on every feeder; compliance motion ≠ fine already imposed. Primary: Genera / energia.pr.gov, received 9 Sep 2026.
Fonte: Negociado de Energía de Puerto Rico. https://energia.pr.gov/wp-content/uploads/sites/7/2026/09/20260909-MI20240005-Motion-in-Compliance-with-Resolution-and-Order-of-August-31-2026.pdf